Project Management Professional-Chapter 11b (Answer key)

Mô tả tài liệu
  Download Vui lòng tải xuống để xem tài liệu đầy đủ

Chapter 11b: Answer key about SCOPE MANAGEMENT 1. Answer: b Scope definition is defined by PMI as ‘‘decomposing the major deliverables into smaller, more manageable components to provide better control.’’ 2. Answer: a The chart of accounts is the system used to monitor project costs as defined by PMI. 3. Answer: c A stakeholder is an individual or organization that is involved in or may be affected by project activities. 4. Answer: c The actual payback period is between two years and three years. It is the point where the net or cumulative cash flows equal zero. This occurs between year...