Project Management Professional-Chapter 12b (Answer key)
lượt xem 41
download

Project Management Professional-Chapter 12b (Answer key)

Chapter 12b: Answer key about TIME MANAGEMENT Answers to the following questions can be found in chapter 2, ‘‘Time Management,’’ unless otherwise noted. 1. Answer: b Note that activities in a calendar schedule start on the beginning of the time period that they start on and end at the end of the time period that they finish on. A two-day activity starts on May 5 and ends on May 6, ES and EF. 2. Answer: b The free float or slack is the amount of time that an activity can be delayed before it affects the schedule of any other activity....