Chapter 17b: Answer key about CONTRACTS AND PROCUREMENT 1. Answer: b A statement of work is the description of what the project is about and what will be delivered. The project plan is complete and contains the detailed work that the project will do, complete with task descriptions and schedule, cost, and scope baselines containing a real schedule and budget. An exception report describes items that are not as planned, and a Pareto analysis is a quality management tool used to prioritize defects into the most frequently occurring. 2. Answer: a In a fixed price contract the supplier is obligated to...