GEOPET Well Completion and Stimulation 4
Once the design well depth is
reached, the formation is tested
and evaluated.
To complete the production well,
casing is installed and cemented,
and the drilling rig is dismantled.
A service rig is brought in to
perforate the production casing
and run production tubing along
with downhole equipments.
Production begins after surface
safety equipment installation
inished.
INTRODUCTION
30’’ CASING
20’’ CASING
13 3/8’’ CASING
7’’ LINER
RESERVOIR
SEA BED
PLATFORM
Production casing (9 5/8)