Industrial Machinery Repair Part 02
Overdue work should be tracked and brought up-to-date. Preventive maintenance scheduling should make sure that the interval is maintained between preventive actions. For example, if a preventive task for May is done on the thirtieth of the month, the next monthly task should be done during the last week of June. It is foolish to do a preventive maintenance task on May 30th and another June 1st, just to be able to say one was done each month. In the case of preventive maintenance, the important thing is not the score but how the game was played....